Joules · weight 30%
Energy throughput
No verified annual energy-consumption figure was found, so this category is unscored.
Entity dossier · Nº 003
Rapid Colossus build-out created one of the world's largest GPU clusters; no policy evidence available. Model synthesis · opinion
Index composition
65% measured · 35% opinion · methodΔ = change vs run N-1 (2026-10-08). Index = weighted mean of the scored categories (weights renormalized over what was scored) · coverage 47% · confidence 25% · measured share 43% of the scored weight (opinion 57%). No “overall” is asked of the model. Scores are AI-assisted (disclosures).
Every published measurement, newest first. N is the run on the leaderboard now; failed attempts are not shown. Unranked runs show no Index; Δ and the Index trend compare ranked runs only.
| Run | Published | Index | Δ | K-equiv | Method | View |
|---|---|---|---|---|---|---|
| N current | 2026-10-13 | 8.2 | +0.7 | — | pipeline-v2.13 · prompts-v2.5 · rubrics-v1 · weights-v1 | viewing |
| N-1 | 2026-10-08 | 7.6 | — | — | pipeline-v2.2 · prompts-v2.2 · rubrics-v1 · weights-v1 | View run N-1 |
| N-2 | 2026-10-08 | Unranked | — | — | pipeline-v2.1 · prompts-v2.1 · rubrics-v1 · weights-v1 | View run N-2 |
Joules · weight 30%
No verified annual energy-consumption figure was found, so this category is unscored.
Watts of thought · weight 20%
Reported operating data-center capacity: 1.5 GW (May 2026) = 1,500 MW → score 7.9.
Total Current Generation Capacity: ~1.5 GW across both sitescleanview.co · fetched 2026-10-13 ↗
Slope · weight 15%
Fewer than two comparable annual figures were found, so growth is unscored.
Opinion · Capability · weight 15%
Built Colossus to 200k Hopper GPUs with plans for >1M H100-equivalents; large-scale frontier training cluster.
Soon, xAI will double the size of Colossus to a combined total of 200,000 NVIDIA Hopper GPUsweb.archive.org · fetched 2026-10-13 ↗
ending the year with over one million H100 GPU equivalentsx.ai · fetched 2026-10-13 ↗
Opinion · Shipping · weight 12%
Colossus 1 fully operational in 122 days / 4 months; workloads running 19 days after first servers delivered.
Colossus 1 was powered up in September 2024, just four months after the first VoltaGrid mobile generators arrived on sitecleanview.co · fetched 2026-10-13 ↗
Colossus was fully operational in 122 days and started running workloads just 19 days after the first servers were deliveredweb.archive.org · fetched 2026-10-13 ↗
122 days and running workloads 19 days after first server delivery, with plans to double to 200,000 Hopper GPUssavrn.com · fetched 2026-10-13 ↗
Opinion · Policy · weight 8%
No public positions or actions on permitting, energy or regulation provided.
| Metric | Value | Period | Source |
|---|---|---|---|
| Data-center capacity (operating) | 1,892 MW | 2026 | savrn.com ↗ |
| Data-center capacity (operating) | 1.5 GW | May 2026 | cleanview.co ↗ |
| Data-center capacity (operating) | 1,300 MW | May 2026 | cleanview.co ↗ |
| Stage | Status | Time | Web searches |
|---|---|---|---|
| resolve | succeeded | 6.3 s | 3 |
| research | succeeded | 22 s | 3 |
| edgar | skipped | 0.0 s | — |
| fetch | succeeded | 1m 44s | — |
| extract | succeeded | 19 s | — |
| compute | succeeded | 0.0 s | — |
| judge | succeeded | 16 s | — |
| aggregate | succeeded | 0.0 s | — |
pipeline-v2.13 · prompts-v2.5 · rubrics-v1 · weights-v1 · bundle 84d74e4a87a6 · code 41d8b4c